20th October
Filming the opening sequences.

22nd October 
Filming the multitude of different female close-ups. 

23rd/24th October
Filming on site at Covent Garden for the market scene and Regent's Park.

27th October
Either repeat of the previous filming of opening sequences if necessary for extra footage. If not then we start filming the street scene at Oxford street. 

29th October
Same here again if we need to achieve more footage for the close ups then we will continue with this. If not we will move on to the street scene at Oxford Street.

3rd November
Draft Video edited and finished.

5th and 9th November
Extra footage is filmed if necessary.

12th November
Filming ends and Editing begins. 

26th November
Editing finishes and music video is completed. 